MIMOSA MINE-NEW FLOTATION CELLS & MODIFICATIONS

Project Info

  • Construction Date

    October 2014 to September 2015

  • Category

    1

Project Name MIMOSA MINE-MODIFICATIONS TO 16No. 5M3 FLOTATION CELLS(TANKS) COMPLETE WITH FLOATATION DRIVE UNITS
Client Mimosa Mine
Engineers/Architect/Main Contractor METSO Minerals
Period October 2014 to September 2015
Scope To dismantle existing cells, fabricate extension materials and adjust Tank capacity by increasing top section and add peripheral launder system. Machine and extend the floatation drive shafts, refurbish Tanks and assemble