BNC SHANGANI MINE – MODIFICATIONS TO UNDERGROUND LEVEL CONVEYOR.

Project Info

  • Construction Date

    2006 - 2007

  • Category

    1

Project Name BNC SHANGANI MINE: MODIFICATIONS TO UNDERGROUND LEVEL CONVEYOR, CRUSHER & ORE PASS CHUTES AND PROVISION OF SKILLED LABOUR FOR OTHER MAINTENANCE WORKS
Client Shangani Mine
Engineers/Architect/Main Contractor BNC Shangani Mine
Period 2006 – 2007
Scope Supply fabrication and erection of chutes, modifications to conveyor and crusher at 915 Level. Provision of skilled labour and equipment for Mine maintenance works